A federal agency that pays a business late owes interest, automatically, at a rate the Treasury sets. When the bill is due, what makes an invoice proper, and how to collect the penalty.

Reviewed by Jake Lawrence on 3 min read

If your business sells to the federal government, a late payment comes with interest. The Prompt Payment Act requires a federal agency that does not pay a business for delivered property or services by the required payment date to pay an interest penalty, and to pay it without being asked.

Who it covers

The Act covers agencies of the federal government buying from a business concern, which it defines as a person carrying on a trade or business, or a nonprofit operating as a contractor. It does not set the rules for a state or city agency's bills, or for a private customer; those run on the contract and state law.

When the bill is due

  • The contract date. If the contract sets a payment date, that is the required payment date.
  • Otherwise, 30 days. If no date is set, payment is due 30 days after the agency receives a proper invoice.
  • When an invoice counts as received. Generally the later of the day the designated office actually receives a proper invoice, or the seventh day after delivery or completion, unless the agency accepted sooner or the contract allows a longer acceptance period.
  • A faster goal for small businesses. Where the contract sets no date, the regulations must require agencies, to the fullest extent permitted by law, to set an accelerated payment date with a goal of 15 days for small business prime contractors. The Fiscal Service says agencies should pay early when an invoice is proper, early payment is in the government's interest, and the invoice is under $2,500, the payee is a small business, or the payment relates to an emergency, disaster or military deployment.

A proper invoice

An agency must review an invoice as soon as practicable and return an improper one within 7 days of receipt, naming every defect. If it takes longer than that, the days it has to pay the corrected invoice shrink by the delay. Send the invoice to the office the contract names, with everything the contract asks for.

The interest penalty

  • Rate. The Treasury sets it. For July 1 to December 31, 2026, the Fiscal Service lists the Prompt Payment interest rate as 4.75%, and it publishes an interest calculator.
  • Period. From the day after the required payment date to the day payment is made, on a 360-day year.
  • Automatic. A business is entitled to any penalty of $1.00 or more without asking, and the payment must come with a notice stating the amount, the rate and the period.
  • Compounding. A penalty unpaid after any 30-day period is added to the principal, and interest accrues on it.
  • Limits. The penalty stops accruing after one year, or once a claim is filed under the Contract Disputes Act.
  • No excuse. A temporary lack of funds does not relieve the agency of the penalty.

If the agency leaves out the interest

If the agency pays but leaves out the penalty, does not pay it within 10 days, and you make a written demand within 40 days of the payment, you are entitled to the penalty plus an additional penalty set by regulation. Mark the 40 days on the calendar.

Discounts and disputes

An agency offered a discount may take it only if it pays within the discount period, counted from the date of the invoice. A discount taken late earns interest on the amount wrongly taken. The Act does not require a penalty on a payment held up by a genuine dispute over the amount or over contract compliance; that goes through the Contract Disputes Act. On federal construction contracts, the prime contract must require the prime contractor to pay subcontractors for satisfactory performance within 7 days out of what the agency paid it, with an interest penalty if it does not, subject to withholding the subcontract allows.

Steps

  1. Read the payment clause and invoice instructions in the contract.
  2. Send a complete, proper invoice to the named office, and keep proof of when it arrived.
  3. Count the due date and check each payment for the interest notice.
  4. Demand a missing penalty in writing within 40 days.

The Fiscal Service's Prompt Payment help line is 800-266-9667. Terms with private customers work differently; see payment terms, explained.

Sources

  1. 31 U.S.C. 3901, Prompt Payment Act definitions and application (Cornell LII) law.cornell.edu
  2. 31 U.S.C. 3902, Prompt Payment Act interest penalties (Cornell LII) law.cornell.edu
  3. 31 U.S.C. 3903, Prompt Payment Act regulations, including the required payment date (Cornell LII) law.cornell.edu
  4. 31 U.S.C. 3904, limitations on discount payments (Cornell LII) law.cornell.edu
  5. 31 U.S.C. 3905, payment provisions relating to construction contracts (Cornell LII) law.cornell.edu
  6. 31 U.S.C. 3907, relationship to other laws, including disputes (Cornell LII) law.cornell.edu
  7. 5 CFR 1315.4, prompt payment standards and required notices to vendors (Cornell LII) law.cornell.edu
  8. 5 CFR 1315.10, late payment interest penalties (Cornell LII) law.cornell.edu
  9. Bureau of the Fiscal Service: Prompt Payment, including the current interest rate fiscal.treasury.gov

How this page was made

Drafted with a language model from the sources above. Jake Lawrence read it against those sources and signed it on November 17, 2026. General information, not legal, tax or financial advice: nothing here answers one business's situation, and every lender and supplier sets its own terms. Found an error? See Corrections.

The Prompt Payment Act: when a federal agency pays late | Credit CEO